Utilities · field work with Airweb

Measuring a power line, pole by pole, from the air.

Heights, wire clearances and span lengths, read off a measurable 3D of each pole and checked point by point against the drone’s own LiDAR. Open a pole in a browser, read the numbers, and repeat along the line. Nobody climbed and no road was closed.

A wooden power pole rebuilt in 3D with four crossarms, its wires running off to one side and a bird’s nest on top, against sky and trees
Our own reconstruction of one pole, from a single drone flight. The line is not identified and nothing here locates it.
The problem

Thousands of poles, and a survey crew for each one.

An owner needs heights, clearances and span lengths for every pole on a line, and the line has thousands. Sending a crew to each one is slow and expensive, and photographs on their own give a picture rather than a measurement. The question was never whether a pole can be photographed. It is whether anything on the resulting record can be trusted enough to act on.

A photograph is not a measurementand a record made of photographs cannot answer how high, how close or how far without somebody going back out.
The clearance question has a date on itvegetation grows, so a distance to a wire is only worth reading with the day it was read attached.
Nobody can say which figures to trustif every pole on the record carries a number and no pole carries the check behind it.
Why this gets commissioned

A network is an asset nobody can afford to visit.

A distribution line is thousands of near-identical structures spread over open country, most of them reachable only on foot or from a track. Everything an owner has to decide about it depends on dimensions, and gathering dimensions is the part that costs real money. So inspection is rationed, the record ages between visits, and the gap between what is on file and what is standing in the field widens quietly.

Clearance work is driven by distances nobody has measured recently

How close the growth has come to the conductor decides where a cutting crew goes next. That decision is usually made from a patrol note or an estimate from the ground, because the alternative is measuring it properly on every span.

A span is the unit the work is planned in

Crews are dispatched span by span, so a figure attached to a whole circuit is not actionable. A figure attached to a span, with the date it was read, is.

Access is the expensive part, not the measuring

Reaching a pole is a vehicle, a track, a landowner and most of a day. Once somebody is there, measuring is quick. That is why anything that answers the question without the journey changes the arithmetic.

The record is held by whoever last changed it

Each crew knows what they did. Nobody holds the current whole, which is how two teams in one business end up planning from different versions of the same line.

What it changes

What it changes.

Dimensions without a journey per pole

Pole heights, crossarm heights, span lengths and the clearance under the lowest wire, read off the 3D instead of off a crew’s day.

Clearance by span, with a date on every figure

The closest vegetation to the wires on each span, so the next flight shows what has grown back rather than starting again.

Every figure carries the check that produced it

Each one is stated as agreement with the LiDAR rather than asserted on its own. That is what lets somebody outside the team argue with it.

The poles that are not good enough say so

Two of the eight were reported as needing a re-flight rather than shown inaccurately, which is more useful than eight poles where nobody can say which two are wrong.

What it is used to decide

The questions it is there to answer.

A record is worth what it lets somebody decide. These are the decisions this one supports, and none of them is made by the model: each is a person deciding, with measurements in front of them instead of an estimate from the ground.

Which spans does the cutting crew go to first?The closest vegetation to the wires is given per span, so the list is ordered by distance rather than by who reported it. On this line two of the seven spans carry growth inside three metres of the conductor and five do not.
Is the clearance under this span what we think it is?The lowest wire at mid-span is measured on each one. Where it disagrees with the record you hold, you know which span to look at before anybody drives out.
Can we plan the work from this, or do we need a survey?Every figure is published as agreement with the LiDAR, so an engineer can see the size of the uncertainty before deciding whether it is small enough for the decision in front of them.
What changed since the last flight?Everything is dated, so a repeat flight is a comparison rather than a fresh start. Growth is the thing that moves, and it is the thing the dates are there for.
The readings

What was measured, and what it was measured against.

Every figure on this page says what kind of figure it is. That is the whole of why it can be used.

8 cmmedian gap between our 3D and the LiDAROver 143,547 points compared on one pole. Measured.
28 cmand nine points in ten fall inside thisThe spread matters more than the middle. Measured.
18.99 mpole height, against 18.92 m from the LiDARMeasured. Seven heights were checked this way, including six crossarms, all within 30 cm.
6 of 8poles placed and checked along the lineChecked by a person against the LiDAR, pole by pole. The other two were reported as needing a re-flight rather than shown inaccurately.
about 1 mbefore the LiDAR check, from positioning aloneMeasured. It is the check that takes it to centimetres, which is why the check is the headline and not the flight.
Span by span

Seven spans, and the two a cutting crew would go to first.

The lowest the wire gets at mid-span, and how close the nearest growth comes to it, for every span on this stretch. 2 of the 7 carry vegetation inside 3 m of the conductor. Read on 10 November 2026 from a scan flown on 18 October 2024, which is the gap every one of these figures has to be read with.

SpanLowest wire at mid-spanClosest vegetation to the wires 
Span 19.63 m6.66 mclear at 3 m
Span 29.37 m4.66 mclear at 3 m
Span 36.55 m2.51 mgrowth inside 3 m
Span 45.84 m3.17 mclear at 3 m
Span 57.65 m1.86 mgrowth inside 3 m
Span 66.46 m5.13 mclear at 3 m
Span 77.63 m4.56 mclear at 3 m

Read from the drone LiDAR and from our 3D of the same poles. The LiDAR is the reference. Distances in metres. The line is not identified and nothing here locates it.

Drone LiDAR points laid over our faded 3D of the same pole: the pole and its fittings picked out, the wires running off to one side, the vegetation below
One pole, LiDAR-checked. Captured by Airweb’s drone pilot network.

The check behind every figure above: the drone’s own LiDAR laid over our 3D of the same pole. Half the points agree within 8 cm and nine in ten within 28 cm, over 143,547 points. Before that fit, positioning alone placed the pole to about 1.0 m.

Honestly

What this is not.

Not survey grade

An engineer confirms before a decision. These figures are good enough to see with, compare with and plan with. They are not good enough to settle anything.

Not our accuracy to claim

Everything is stated as agreement with the LiDAR. The LiDAR’s own accuracy belongs to its vendor.

Where a surveyed figure exists, it wins

These are good enough to see with, compare with and plan with. They are not good enough to settle a boundary, a clearance breach or a claim.

Not a current clearance record

It describes the line as it was scanned in October 2024. Vegetation in particular has moved, which is why every figure carries its date rather than being presented as today.

No saving is claimed, because none was measured

The obvious thing to put here is crew visits avoided. Nobody measured that, so there is no figure for it and we are not inventing one.

Captured by Airweb’s drone pilot network. The flying is theirs and the reading is ours. Their logo is their own, shown on a dark panel of ours so it is legible here.

Questions we get asked

Before you ask.

Is this survey grade?

No. It is for an engineer to confirm before any decision rests on it. Where a surveyed figure exists, the surveyed figure wins. What this does is put a measurement where there was previously an estimate from the ground.

How accurate is it, really?

On the pole we checked in full, half the points sit within 8 cm of the LiDAR and nine in ten within 28 cm. Along the line, the poles that passed are typically within 10 to 25 cm. Those are agreements with the LiDAR, not absolute accuracies: the LiDAR’s own accuracy is its vendor’s to state, not ours.

Why does the LiDAR matter if you have the 3D?

Because a measurement with nothing to check it against is an opinion with a decimal point. Positioning alone places a pole to about a metre. Fitting it to the LiDAR the same aircraft collected is what takes it to centimetres and makes the numbers worth printing.

What happened to the two poles you left out?

The flights we had would not place them to the same standard, so they were reported as needing a re-flight. Publishing eight numbers where six are checked would have made the whole record worth less, not more.

Are the vegetation figures still true?

They describe the line on the day it was scanned, 18 October 2024, and they were measured from that scan on 10 November 2026. Growth has moved since. That gap is why every clearance figure on this page carries its date, and why the value of this is in repeating it rather than in any single pass.

How much does it save?

We do not know and we will not put a figure on it. Nothing about time or cost was measured on this job. The obvious claim would be crew visits avoided, and we would be making it up.

What does it need from us?

One routine drone flight per pole, flown by pilots who already fly them, and the LiDAR from the same aircraft. No ground markers, no road closure and nobody climbing. If you already hold suitable footage and LiDAR, we will look at that first.

Does it work on steel, or only wood?

This line is wood. The method does not care what the pole is made of, but we would want to see footage of the structure before saying what reads well on it. Lattice and narrow steel are harder, because there is less surface for the flight to see.

Who owns the output?

You do. The flying is the partner’s and the reading is ours, and what we hand over is yours to keep and put in front of an engineer.

Got a structure nobody can see all of?

Tell us what it is and what you need to know about it. We will say whether this would answer it, including when it would not.